Solutions
Project & Budget ManagementExpense & Finance TrackingPower Features
PricingFree ToolsBlogAbout UsResources
Open ARC PEMAccount & billingGet started
Blog / GST & Compliance
GST & Compliance

Is a Pollution Ban Force Majeure? GRAP Construction Stoppages and Your Contract (India 2026)

Does a GRAP or CAQM construction ban count as force majeure? What Indian law, RERA and your contract say, plus a clause you can use in new contracts.

Construction contract open at the force majeure clause, with a halted Delhi-NCR site under smog in the background

Short answer: A GRAP or CAQM construction ban can be force majeure, but only if your contract's force majeure clause covers government or statutory orders, the ban actually stopped your work, and you gave notice on time. Even then, it usually gets you more time, not more money. Under RERA, a builder may find it harder to extend the possession date because of a pollution ban, because the Act's own definition of force majeure is narrow.

The CAQM order of 30 October 2026 stopped outdoor construction across Delhi-NCR from 5 to 20 November 2026, and GRAP Stage III ran from 6 to 17 November. Contractors, builders and architects now have the same question: who bears the delay? This article explains how force majeure works for pollution bans under Indian law. For the current ban status, see our Delhi-NCR Construction Ban 2026 guide.

What "force majeure" actually means in Indian law

Force majeure is not a general legal right. It is mainly a contract clause. Indian law looks at it in two ways:

SituationLaw that appliesWhat it means for you
Your contract has a force majeure clauseSection 32, Indian Contract Act, 1872 (contingent contracts)The clause's own wording decides what counts and what relief you get
Your contract has no such clauseSection 56 (frustration/impossibility)Relief only if performance becomes impossible. A temporary 16-day ban almost never qualifies

The Supreme Court made this distinction in Energy Watchdog v. CERC (2017). It also held that force majeure is read narrowly: a contract becoming harder or costlier to perform is not enough.

Practical takeaway: Your contract matters far more than the law in general. Read the clause before you write to anyone.

The four tests a GRAP ban must pass

1. Is the event covered by the clause?

Look for wording such as:

  • "acts of government" or "orders of any statutory or governmental authority"
  • "change in law"
  • "restrictions imposed by any court or authority"
  • an open-ended phrase such as "any other cause beyond the reasonable control of the parties"

The CAQM is a statutory body under the Commission for Air Quality Management Act, 2021, and its orders are legally binding. A clause that covers statutory orders generally covers a CAQM direction. A clause that lists only "flood, fire, earthquake, war, epidemic" may not, unless it also has a catch-all phrase.

2. Did the ban actually prevent your work?

Force majeure excuses only the work that was actually stopped.

  • Exempt projects (Metro, railways, airports, hospitals, defence, projects of national importance) cannot claim it.
  • Indoor work (plumbing without open trenches, electrical, carpentry, finishing) often continued, so those days are not a delay.
  • Work that was already behind schedule before the ban cannot be blamed on it.

3. Was it unforeseeable?

This is the weakest point for pollution bans. GRAP has been invoked in NCR every winter for several years. An employer may argue that a contractor signing in, say, August 2026 should have priced in winter stoppages.

Counter-arguments that help the contractor:

  • The dates and length of a specific order cannot be predicted.
  • The 2026 order also covered linear projects and went beyond the standard GRAP schedule.
  • Many clauses do not require unforeseeability at all. Check whether yours does.

4. Did you give notice as the contract requires?

Many contracts say relief is conditional on written notice within a fixed number of days (often 7, 14 or 28). Missing that deadline is the most common reason valid claims fail. Notice must be written: a letter plus an email, citing the order and the clause. A phone call or WhatsApp message is not enough.

Time, money or termination: what relief do you get?

ReliefUsually available?Notes
Extension of timeYes, in most clausesCovers the stopped days plus reasonable remobilisation time
Protection from liquidated damagesYes, follows the extension of timeThe client should not deduct LD for excused days
Idle / standby costOften noMany clauses say "each party bears its own costs". A change-in-law clause may allow costs
Price escalationOnly if there is an escalation clauseForce majeure does not cover material price rises
TerminationOnly after a long stoppageClauses often allow it after 60–180 continuous days. Not relevant for a 16-day ban

For the step-by-step claim (notice format, hindrance register and idle-cost calculation with a worked example), see our guide on construction ban delay claims and extension of time.

Who can claim against whom?

  • Contractor vs client/employer: the most common claim, mainly for extension of time.
  • Subcontractor vs main contractor: the subcontract's own clause applies. A "back-to-back" clause usually gives the subcontractor only what the main contractor recovers.
  • Architect or PMC: usually certifies the extension. Fee contracts may also allow a fee extension if the project runs longer. Check your appointment terms (see Architect Fees in India).
  • Builder vs homebuyer: handled differently, because RERA applies. See the next section.

The RERA trap for builders

Builders often assume a construction ban automatically extends the possession date promised to buyers. It may not.

Section 6 of the Real Estate (Regulation and Development) Act, 2016 lets the authority extend a project's registration for force majeure, but the Act's explanation defines force majeure as war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature. A government order is not on that list.

What this means in practice:

  • A builder may not be able to rely only on a GRAP ban to avoid interest to homebuyers for delayed possession.
  • In past disputes, consumer forums have rejected pollution-ban defences where the builder could not show the specific orders, dates and actual effect on the project.
  • During COVID, some state RERA authorities issued blanket extensions by notification. No such extension has been announced for the 2026 GRAP bans so far.

What builders should do: keep a day-by-day record of every stoppage, linked to the official order. Apply to your state RERA authority for an extension if the delay is significant. Build realistic winter buffers into the possession dates you promise from now on.

Clause you can use in new contracts

GRAP will return next winter. Avoid the argument altogether by writing it into new contracts. A sample clause (have your lawyer adapt it):

Statutory Environmental Restrictions. If construction or any part of the Works is suspended or restricted by an order of the Commission for Air Quality Management, any action under the Graded Response Action Plan (GRAP), or any direction of a court, tribunal or government authority relating to air quality, (a) the Contractor shall notify the Employer in writing within 7 days of the restriction taking effect; (b) the Time for Completion shall be extended by the number of days on which the affected work was actually restricted, plus up to [5] days for remobilisation; (c) no liquidated damages shall apply for that period; and (d) [each party shall bear its own costs] / [the Employer shall reimburse documented standby costs for retained staff and hired equipment up to [__]% of the Contract Price].

Pick one option in (d) and agree it before signing. That one choice settles the most common dispute.

Also review:

  • Programme: schedule dust-heavy work (excavation, demolition, external plaster) outside November to January where possible.
  • Pricing: include a winter contingency for NCR projects.
  • Payment schedule: avoid milestones that fall in mid-November. See Construction Payment Schedule.

Quick checklist: can you claim force majeure for the 2026 ban?

  • ☐ The clause covers government, statutory or court orders (or has a catch-all)
  • ☐ Your project was not exempt under the 30 October order
  • ☐ Specific activities were stopped (not indoor work that continued)
  • ☐ You were not already in delay for other reasons
  • ☐ You sent written notice within the contract deadline
  • ☐ You have the official order copy, DPRs and a hindrance register
  • ☐ You know whether your clause gives time only, or time and money

If you can tick every box, your claim is strong. If you can't tick the notice box, send notice now and get legal advice.

Record every stoppage in ARC PEM

A force majeure claim is only as strong as your records. In ARC PEM, log stoppage days against the project and tag idle labour, equipment rent and overheads to a separate cost head. You can then show the client, a RERA authority or an arbitrator exactly what the ban cost, with dates and bills.

Try ARC PEM free →

Key takeaways

  • Force majeure in India is mainly contractual (Section 32). Without a clause, you need impossibility under Section 56, which a short ban rarely meets.
  • A CAQM or GRAP order is a statutory order. It is covered if your clause includes government or statutory orders.
  • Relief is usually extension of time and protection from LD, not idle-cost payment.
  • Notice on time is often a condition of relief.
  • RERA's definition of force majeure is narrow, so builders should not assume a pollution ban extends possession dates.
  • Put a specific GRAP clause in every new NCR contract.

This article is general information, not legal advice. For disputed claims or large amounts, consult a construction lawyer.

Sources

  • Indian Contract Act, 1872: Sections 32 and 56
  • Energy Watchdog v. Central Electricity Regulatory Commission (Supreme Court, 2017)
  • Real Estate (Regulation and Development) Act, 2016: Section 6
  • Commission for Air Quality Management in NCR and Adjoining Areas Act, 2021
  • CAQM order dated 30 October 2026 and GRAP notices: caqm.nic.in
  • Khaitan & Co, "Delhi High Court deals with the force majeure clause in construction contracts"

Frequently asked questions

Is a GRAP construction ban force majeure?
It can be. If your contract's force majeure clause covers government or statutory orders, a CAQM or GRAP order generally qualifies for the days it actually stopped your work. If the clause lists only natural events with no catch-all phrase, it may not be covered.
What if my contract has no force majeure clause?
Section 56 of the Indian Contract Act then applies, and it requires performance to become impossible. A temporary ban of a few weeks rarely meets that test, so you would negotiate an extension under the contract's general extension-of-time clause instead.
Does force majeure let me recover idle costs?
Usually not. Most force majeure clauses give extra time and protection from liquidated damages, with each party bearing its own costs. Costs may be recoverable under a change-in-law clause or a specific standby-cost provision.
Can a builder extend the RERA possession date because of a pollution ban?
Not automatically. RERA Section 6 defines force majeure as war, flood, drought, fire, cyclone, earthquake or a natural calamity, and government orders are not listed. Builders should keep detailed stoppage records and apply to the state RERA authority.
Is a GRAP ban foreseeable, since it happens every winter?
An employer may argue so. However, the timing and length of a specific order cannot be predicted, and many force majeure clauses do not require unforeseeability. The exact clause wording decides it.
How should new contracts handle GRAP bans?
Add a specific clause covering CAQM, GRAP and court orders on air quality. It should set the notice period, extension-of-time days, remobilisation days, LD relief, and whether standby costs are paid.
Free Demo · No Credit Card Required

Ready to take control of
your project finances?

Join the architecture and construction firms already using ARC PEM to track budgets, manage vendors, and generate professional reports — without a single spreadsheet.

Start your plan
Arch Consultancy logoMunesh Associates logoSS Constructions logoSai Builders logo
Trusted across India
by architects, interior firms & builders
Bank-grade SecurityEncrypted, isolated per firm
Monthly or annualAuto-renews · cancel anytime
+91-8810235570Talk to sales · Mon–Sat
info@arcpem.comWe reply within 24 hours
Get Started Free →View Pricing