Building plan approval in Delhi-NCR is not one process. It is at least five. Delhi, Noida, Gurugram, Ghaziabad and Faridabad each have their own authority, portal and bye-laws. Most of them have moved online, and several changed their rules in 2025 and 2026. For an architect or a construction firm working across the region, a delay in sanction usually costs more than any single line in the estimate.
This guide sets out who approves what, the documents you need, what changed this year and how approvals fit around the winter construction restrictions.
Check before you file. Portals and bye-laws change often, and some 2026 changes below are approved but not yet confirmed as notified. Confirm the current rules with the local authority or an empanelled architect. This article is general information, not legal advice.
Who approves building plans in Delhi-NCR?
| Area | Authority | Portal (as reported) | Status to check |
|---|---|---|---|
| Delhi (MCD areas) | MCD, under the Unified Building Bye-Laws (UBBL) 2016 | MCD online building plan sanction (eodb.mcd.gov.in) | DDA's amendments to UBBL approved on 12 Aug 2026; confirm whether notified |
| Delhi (DDA land) | DDA | DDA online building permit system. AI-enabled single window launched 12 May 2026 | New system covers plan submission, uploads, fees and tracking |
| Noida | Noida Authority | Online building plan approval system (reported as upobpas.in) | No official 2026 notice found; confirm |
| Greater Noida | Greater Noida Authority | Authority's online approval system | Reported to allow CoA-registered architects to sanction plans for individual residential plots |
| Gurugram, Faridabad (municipal areas) | Urban Local Bodies, Haryana | OBPAS (obpas.ulbharyana.gov.in) | Haryana is moving to fully online approvals with fixed timelines |
| Gurugram, Faridabad (HSVP sectors) | HSVP | obpas.hsvphry.org.in | Allottees pick an empanelled architect through the portal |
| Ghaziabad | GDA | GDA online map approval | Paused in July 2025 to apply revised UP bye-laws; confirm it has resumed |
If your plot is in a licensed colony, a sector or an industrial area, the approving body may differ again. Always check which authority holds your land first.
What changed in 2026
- Delhi, DDA single window (12 May 2026): An AI-enabled system under the online building permit system, which checks uploaded drawings against UBBL and flags deviations.
- Delhi, UBBL amendments (approved 12 Aug 2026): DDA approved changes to simplify approvals, including removing the need for separate NOCs from bodies such as the DPCC, Chief Inspector of Factories, Delhi Jal Board and Forest Department for building permits. I found no confirmation that they are in force.
- Delhi, Ease of Doing Business Bill, 2026: The Cabinet cleared a draft that would let some categories complete fire safety, building plan and pollution approvals on self-declaration. It is a proposal, not settled law.
- Haryana (April 2026): The state said building plan approvals should become fully online, with clear timelines and accountability for officials.
- Haryana, stilt-plus-four (S+4): Approvals for S+4 residential buildings were reported on hold under an interim High Court stay. Check the current status before designing to S+4.
- Uttar Pradesh: Revised building bye-laws and the UP Model Building Regulations 2026 affect Noida, Greater Noida and Ghaziabad. Details were not available to me, so confirm the current rules with the authority.
Documents usually needed
Requirements vary by authority and plot type. Most applications ask for:
- Ownership proof: sale deed, allotment letter or lease deed
- Mutation certificate or title documents, where applicable
- Site or location plan with plot dimensions and surroundings
- Architectural drawings: plans, elevations, sections and area statement
- Structural stability certificate and structural drawings from a qualified engineer
- Architect's registration (Council of Architecture) and, where required, local empanelment or licence
- Owner's identity and authorisation documents
- Fee payment proof
- Demolition-waste declaration for plots of 200 sq m and above where demolition is involved (CAQM direction, from 1 April 2026)
Keep the file in a consistent format. Most portals now compare uploaded drawings with the bye-laws automatically, so a mismatched area statement is a common cause of queries.
Typical approval steps
- Confirm the authority and the land-use rules for the plot: permissible use, ground coverage, FAR, height and setbacks.
- Prepare drawings through an architect registered or empanelled with that authority.
- Upload on the portal with documents and the structural certificate.
- Pay scrutiny and sanction fees online. Fee schedules differ by authority, so use the authority's current schedule.
- Respond to objections raised on the portal within the stated time.
- Receive the sanctioned plan and keep a copy at the site.
- Start work only after sanction. Then apply for a completion or occupancy certificate when the building is done.
Timelines (reported): Delhi's bye-laws have long allowed sanction within about 30 days, and one 2026 guide says the plan is deemed sanctioned if the corporation does not respond by day 31. Treat that as unconfirmed until you check the bye-laws. GDA's online system reported faster turnaround for small plots when it was running.
Plan approvals around the winter construction restrictions
Delhi-NCR's winter air-quality orders restrict dust-generating construction for weeks at a time. See Delhi-NCR construction ban 2026 for the current position. The practical lesson for scheduling:
- File early. A sanction that arrives in October still leaves little working time before the winter curbs.
- Use the restriction window for paperwork: approvals, tender documents, material orders and mobilisation plans.
- Check site dust compliance before the first day of work. Projects of 500 sq m or more must register on the state or Delhi portal, and CAQM's dust-control rules apply all year.
Common reasons applications get stuck
These are typical queries, not official statistics:
- Drawings that don't match the area statement or the plot dimensions
- Setbacks, ground coverage, FAR or height outside the bye-laws
- Missing or inconsistent structural certificate
- Architect not registered or empanelled with that authority
- Ownership or mutation documents that don't match the applicant
- Unpaid or incorrectly calculated fees
- Plot in a land-use zone that doesn't allow the proposed use
For architects: protect your time and your fee
Approval work takes real hours. Query rounds, re-uploads and site visits all land on your team. Put the approval stage in your fee proposal with a defined number of resubmissions, and bill by stage. See the architect fee proposal format and architect fees in India.
For builders and contractors: budget the approval stage
Approval fees, consultant charges, delays and holding costs belong in the project budget before you commit to a start date. Use the Construction Cost Calculator for an early estimate, check construction cost per sq ft in India by city and align the area statement with built-up vs carpet area.
Track approval costs per project
Approval fees, consultant bills, resubmission time and delay costs add up quietly across projects. Log them against each project from the first week. ARC PEM keeps project-wise expenses so you can see what approvals really cost. See how ARC PEM tracks a project's money end to end.
Key takeaways
- Delhi-NCR has several approving authorities, each with its own portal and bye-laws.
- 2026 brought changes in Delhi (DDA single window, UBBL amendments approved) and Haryana (fully online push, S+4 stay). Confirm what is in force before you file.
- Use an architect registered or empanelled with the right authority.
- Don't start work before sanction, and plan the start date around the winter restrictions.
- Put approval costs and resubmission limits into your budget and your fee proposal.
Sources
- Delhi: DDA AI-driven single-window system (ThePrint)
- Delhi: DDA approves UBBL 2016 amendments (The Pioneer)
- Delhi: Ease of Doing Business Bill (The Pioneer)
- Haryana: Online Building Plan Approval System (ULB)
- Haryana: HSVP OBPAS user manual
- Haryana: fully online approvals (The Week, April 2026)
- Greater Noida Authority: approval of building plans
- Noida Authority online approvals (Millennium Post)
- GDA online map approvals paused (PropNewsTime)
- Commission for Air Quality Management
Updated 16 November 2026. General information only, not legal advice. Confirm current rules with the local authority.