Contingency is an amount added to a construction budget, usually a percentage of the estimated cost, to cover unforeseen work, price rises and small design changes that cannot be priced in advance.
Contingencies of roughly 3% to 10% of project cost are common, with higher figures for renovation work and early-stage estimates, where more is unknown.
Contingency is not a reserve for planned scope. Draw on it only for genuinely unforeseen items and record each use, so the client can see why the budget moved.